Catalog · Institutional specification

5 MW Data Cell & ~6 MW firm Power Cell.

Catalog brick for US AI pads: a 5 MW Data Cell designed for NVIDIA Vera Rubin-class rack-scale systems, and a ~6 MW firm Power Cell (natural gas or power-ready). Units may be ordered paired or standalone. Figures below are indicative design envelopes, not contractual guarantees.

Indicative · Standalone OK · Commercial terms under NDA

No equipment OEM brand names in this public sheet; partner selections are project-driven. NVIDIA Vera Rubin is named only as the hardware platform class the Data Cell is designed for. No partnership or certification is implied.

Matched pair

Why ~6 MW generation for 5 MW IT.

Facility load is not IT nameplate alone. CDU pumps, dry-cooler fans, the trim chiller at peak, electrical losses, and auxiliaries add overhead. With 45 °C warm-water direct-to-chip cooling, peak facility factor is ~1.07–1.16, so ~6 MW firm on the facility bus covers one 5 MW Data Cell with margin for hot-day ambient and BESS recharge.

N+1 gas (3+1 gensets) keeps that ~6 MW continuous with one genset offline. The grid-forming BESS (≥~6 MW PCS, 1–2 h default) carries fast AI load swings and bridges starts. It does not replace continuous megawatts.

Spec board: 5 MW Data Cell (Vera Rubin-class basis, 14 modules) and ~6 MW firm Power Cell (9 or 4 units), next-gen option provisional
Catalog callout — 5 MW IT Data Cell + ~6 MW firm Power Cell; next-gen option provisional.

Unit A · Data Cell

5 MW Data Cell — Vera Rubin-class design basis

Standard buyable 5 MW IT cell, delivered as about 14 factory-built modules. Scale campuses as multiples of 5 MW IT by landing additional cells.

5 MW Data Cell module set with all 14 units labeled
5 MW Data Cell — 14 shipping units: 2 IT · 1 CDU · 2 electrical · 1 network · 7 dry coolers + 1 trim chiller.
5 MW Data Cell specification
Catalog SKU 5 MW Data Cell — designed for NVIDIA Vera Rubin-class rack-scale systems (Vera Rubin NVL72 class)
IT rating Capped at 5.0 MW IT per cell (enforced by power management)
Rack power basis ~330 kW per compute position (design basis; matches N+1 rack power-shelf capacity, with headroom above published rack TDP)
Rack positions 16 compute + 6 network / storage (22 positions); 8 compute + 3 network per IT module; 8 contiguous compute positions per module
Cooling 100% direct-to-chip liquid; warm-water supply up to 45 °C; CDUs N+1 in a dedicated CDU/pump module; 7 adiabatic dry coolers (N+1) + 1 trim chiller
Liquid (indicative) ~500 L/min (~130 GPM) per 330 kW position at ΔT ≈ 10 K; ~8,000 L/min per cell (calculated; confirmed per rack OEM)
Electrical 2 electrical (LV power block) modules; 415/480 VAC A/B busway per IT module; UPS for CDUs, network, and controls; reserved 800 VDC path
IT module envelope ~14 ft W × 45–50 ft L × 11–12 ft clear; steel deck ≥30 kPa in rack zones; dedicated space for manifolds, leak detection, and clean-agent cylinders
Safety Clean-agent total-flooding suppression + VESDA aspirating smoke detection per IT module; zoned leak detection with branch isolation
Power interface Fed from a matched ~6 MW firm Power Cell (gas or power-ready) via a standardized MV/LV interface
Scale-out Multiples of 5 MW IT by adding Data Cells (and matched Power Cells)
Delivery ~14 shipping modules (range 12–17), shipped as oversize permit loads, not standard ISO containers; racks installed on site; field work is foundations, piping, electrical tie-in, commissioning

Module schedule — one 5 MW Data Cell

Data Cell module schedule
Wide IT modules2 — ~14 ft W × 45–50 ft L × 11–12 ft clear; 8 compute + 3 network/storage positions each
CDU / pump module1 (range 1–2) — N+1 CDUs, filtration, expansion, make-up, controls
Electrical modules2 (range 2–3) — LV power blocks, busway feeders, UPS for CDUs / network / controls
Network / MMR module1 (0–1; can merge into an IT module) — spine / aggregation, fiber patching, two diverse carrier entries
Heat-rejection skids7 + 1 (range 6–9 + 1) — adiabatic-assist dry coolers N+1 plus one trim chiller
Total≈ 14 shipping units (range 12–17). The Power Cell is separate (9 units gas / 4 units power-ready)

Next-gen option Provisional

~600 kW/rack · 800 VDC · same 5 MW cell

For the next Rubin Ultra-class generation of rack-scale systems. Every value in this table is provisional until the platform is published and confirmed. The base Data Cell can be built next-gen ready.

Next-gen option (provisional)
StatusNext-gen option / provisional — planning basis only; not a released catalog SKU
Rack power basis~600 kW per compute rack (Rubin Ultra-class), with an 800 VDC power sidecar per rack
Rack positions8 compute racks (~4.8 MW) + 8 power sidecars + 4 network positions, capped at 5.0 MW IT through rack-level power capping
Cooling100% direct-to-chip liquid, up to 45 °C supply; ~900 L/min per rack at ΔT ≈ 10 K; same CDU capacity and heat-rejection plant as the base cell
Electrical800 VDC via sidecars on the AC busway, or centralized DC conversion in the E-House (later); DC-rated protection
StructureHeavier deck (≥50 kPa in compute zones); clear height ≥11 ft
Module set≈ 14 shipping modules (range 12–18), about the same as the base cell, because total heat and power do not change
Next-gen ready base cellOptional provisions at base build: rack-pair layout, larger headers and branch valves, heavier deck, replaceable busway tap-offs, 800 VDC bay and DC pathway, lithium-ion detection and venting

Unit B · Power Cell

~6 MW firm Power Cell

Firm facility bus sized for one 5 MW Data Cell, as a gas package (9 units) or a power-ready package (4 units).

Gas Power Cell with all 9 units labeled
~6 MW firm Power Cell, gas package — metering skid + 4 gensets (N+1) + 3 BESS + E-House = 9 units.
Power Cell 6 MW firm specification
Catalog SKU ~6 MW firm Power Cell — natural gas (Package A) or power-ready (Package B)
Firm output ~6 MW firm on the facility bus per 5 MW IT; warm-water DLC peak facility factor ~1.07–1.16 leaves margin for hot-day ambient and BESS recharge
Package A · gas (9 units) 1 gas metering / regulation skid · 4 genset enclosures (N+1, 3+1) · 3 BESS enclosures · 1 E-House / MV switchgear
Package B · power-ready (4 units) Utility interconnect / substation tie (utility or site scope) · 3 BESS enclosures · 1 E-House / MV switchgear · no gensets
Generation · N+1 Package A: pipeline natural gas (city gate or lateral); 60 Hz reciprocating gensets, 3+1 at ~2.0–2.5 MWe class, so ~6 MW continuous remains with one unit offline
BESS (default) Grid-forming, ≥~6 MW PCS on the facility bus; 1–2 h usable (~6–12 MWh class). Carries rack-scale AI load swings (target: full Data Cell step within ~100 ms) while gensets run ramp-limited. ~4 h only if island / tariff products require it
Electrical BOP Factory E-House / MV switchgear → Data Cell electrical modules (indicative 11–34.5 kV MV class; site-locked); reserved 800 VDC conversion bay
Redundancy philosophy N+1 at genset level for firm continuous MW; the BESS covers sub-second to minutes and does not substitute for missing continuous capacity
Fire / life safety BESS to UL 9540 with UL 9540A test data and NFPA 855 siting; gensets and fuel gas per NFPA 37 / 54
Scale-out One Power Cell per 5 MW Data Cell; campuses grow 10 / 15 / 20 MW IT… with matched ~6 MW firm Power Cells
Delivery Factory-integrated generation, storage, and MV modules; FAT before shipment; field work is foundations, gas or utility tie-in, interconnect, commissioning

Schedule · Indicative

Lead-time notes

Industry / publicly cited ranges—not GridCell commitments. Weeks vary with slot reservation, customization, and logistics.

Indicative lead times
GridCell Order planning (locked) Gas ~34–46 weeks. Power-ready ~28–38 weeks (Data-only follows the power-ready band). Indicative planning bands only, not a contractual guarantee. Final lead times are set in the agreement.
Gas gensets (Americas market context) Industry / publicly cited ranges have historically run ~60–70 weeks and toward ~110 weeks under market pressure. GridCell Order planning uses the shorter locked bands above for indicative scheduling.
BESS (containerized / C&I) Factory cabinets often ~4–8 weeks standard; custom / multi-MWh ~8–16+ weeks; ocean freight often +2–6+ weeks. Distributor tables for 0.5–5 MWh class sometimes ~10–26 weeks.
E-House / MV prefab modules OEM claims of materially shorter delivery/construction/commissioning vs traditional site-built; absolute weeks are project-specific.
Data Cell / modular white space Typically shorter than genset slots; the ~14 Data Cell modules are built in parallel with the Power Cell when ordered together. Prefab modular stacks are sometimes cited at ~6–8 months end-to-end vs conventional 18–24+ months.
Planning implication Treat genset manufacturing slots as critical path. Align ship dates to site pull—early equipment without foundations creates storage risk.

Commercial

Pricing & payment

Commercial terms under NDA / direct quote. Standalone Power Cell or Data Cell orders are allowed. List prices and detailed payment schedules are not published on this public site.

Contact contact@gridcellai.com for a formal quote. No card payments on this site.

Ready to discuss a site package?

Request a quote for 5 MW Data and/or ~6 MW firm Power Cells (standalone OK). Pricing and payment schedule are provided under NDA.

On the pad

One brick. Add by count.

Public buyable catalog stays on the 5 MW IT grammar. Each 14-module Data Cell lands beside its matched ~6 MW firm Power Cell (9 units gas, or 4 units power-ready). Campuses scale 10 / 15 / 20 MW IT… without alternate catalog ratings.

Matched pair on one pad: ~6 MW firm Power Cell (9 units) and 5 MW Data Cell (14 modules)
Matched pair — ~6 MW firm Power Cell (9 units, gas) + 5 MW Data Cell (14 modules).